Fuselage


June
8, 2005
Begin work on center section spar carry through. The center
section carry through comes with the wing kit since it is matched to the wing
spars.
June 10-11, 2005
Preparation work on the center section bulkheads involves
enlarging some holes to accept snap bushings for rudder cables, wiring, etc.,
match drilling components, countersinking and installing platenuts to the top
flange of the bulkheads. I did some cleaning, etching, alodining and
priming of the countersunk holes on the bulkheads to prevent corrosion.

June 12, 2005
Did the prep work for priming the firewall parts and center
section parts. Degrease with Dawn soap and water, acid etch, and alodine.
Pictures from left to right: After acid etching, in the alodine tank, after
alodine step.


June
13, 2005
Primed the firewall and center section parts.

June
14, 2005
Began riveting firewall components (stiffeners, gussets,
brackets) to firewall. Shot bags and clamps help to hold in place while riveting
components together.

June
15, 2005
Completed riveting the firewall components. I supported the
firewall on the floor with clamps, shot bags and the tank stands. Made it much
easier to reach some of the rivets.


June 16, 2005
Here's an aft shot of the firewall. Started riveting the center
section bulkhead components. Again, clamping to the bench holds everything in
position to rivet.

June
17, 25-26, 2005
Completed riveting center section components. At left is the
forward center bulkhead showing the cover support ribs. At right is the aft
center bulkhead with the control column components installed.