Left Wing



March 17-18, 2003
WINGS ARRIVE! Received the wing kit on Monday, March 17. Just some
slight damage to the end of the spar box but it wasn't transferred to any parts
inside.

Beautiful
gold anodized spars and center section. Both crates were well packed by Van's.
It took about 4 hours total to unpack and inventory. Only short 3 washers.
Pretty impressive.

April
19-21, 2003
I only have enough room to build one wing at a time, so I am beginning on the
left wing. The first step is to drill, debur, and countersink holes for the tank
attach platenuts.

View
of top and bottom of the spar flange after installing the tank attach platenuts.

April
23-May 10, 2003
Off to Maui for a little R&R. Went to the beach about every day. A picture of
me and the Mrs. on top of Haleakala volcano at 10,038 ft. msl. This is the
highest point on Maui.

May
15-20, 2003
(Back to REALITY) All the tank attach platenut center holes are machine countersunk for #8
screws.

May
21, 2003
Countersank the spar platenut center holes for the wing inspection covers.
Drilled, deburred and dimpled 3 inspection plate covers. These go on the bottom
wing to allow access to various components within the wing.
May
22, 2003
Cleaned, Acid etched, alodined and primed all the machine countersunk holes
in the spar. This will help to prevent corrosion on the bare aluminum.
Don't want any corrosion on the wing spars!